Hi ,
I have 3 batches of PCs with 3 different Warranty end dates.
Is there a slick way of pointing an Asset , to one of 3 warranty dates?
Thank you in advance
Simon
Jul 12, 2024 05:16 AM
Easiest way would be to create a spreadsheet with the unique asset name and the corresponding warranty end date. Then create a simple business adapter and use the spreadsheet as the source for your update. Thats what I would do 🙂
Jul 12, 2024 06:50 AM
Easiest way would be to create a spreadsheet with the unique asset name and the corresponding warranty end date. Then create a simple business adapter and use the spreadsheet as the source for your update. Thats what I would do 🙂
Jul 12, 2024 06:50 AM
Nice one , thank you
Jul 12, 2024 06:51 AM
I have also discovered that Contracts is a great place to file specific Extended Support Packages and I have been able to link 'many to one'
Jul 15, 2024 01:10 PM