Up to now we do not use this feature, which means that we have no value entered in the field "Inactivate Asset after x day" within our Standard mandator.

Now  (some days ago) I have set this value to 90 on our test system, but no assets changes it status to "Not reported by SWR".
1. Is there anything else to do?
2. On wich date this 90 days will be calculated, lastScanDate or SWRUpdateDate?

2019-11-05 13_55_44-Microsoft Edge.png

Thanks and Regards Markus

(1) Solution

Hi Markus,

 

I am wondering if you have the following parameters in Spider Admin > Spider Asset - Object definition > Asset > Asset Status:

james_ellis_0-1573036745715.png

 

It seems that the SWR is missing the NotReported Status.

 

Kind regards,

James Ellis

 

Like the answer, please remember to "Accept as solution". Keep the Kudo's coming!

View solution in original post

(3) Replies

Hello,
this option is based on "Last scandate", when I sort Assets by Last scandate I can clearly see when 90 days passed.
Then the license requirement of Asset is 0.
but unfortunatelly, there are still assets which are not imported from inventory for a while...

 

Vlad

But I can see GREEN dot "Configured" status.

Hi Markus,

 

I am wondering if you have the following parameters in Spider Admin > Spider Asset - Object definition > Asset > Asset Status:

james_ellis_0-1573036745715.png

 

It seems that the SWR is missing the NotReported Status.

 

Kind regards,

James Ellis

 